By when must a complete drawback claim be filed?
- Within 180 days after liquidation of the import entry
- Within 1 year after exportation
- Within 3 years after the date of importation
- Not later than 5 years after the date on which the designated merchandise was imported
Show the answer
D. Not later than 5 years after the date on which the designated merchandise was imported
A complete drawback claim is timely if successfully transmitted not later than 5 years after the date on which the merchandise designated as the basis for the claim was imported.
Source: 19 CFR 190.51(e)(1)